Gullen Solar Farm was awarded a grant from the Australian Renewable Energy Agency (ARENA) in 2016 under their Advancing Renewables Program. You can read more about the project on the ARENA website here.

As a requirement of the grant, certain information about Gullen Solar Farm and its operation is made available on our website.

The final capital expenditure (CAPEX) required to construct the project was $24.8 million, compared to a forecast of $25.3 million.

Information about the project (the static project data) can be downloaded here. This includes specific information about the quantity and type of equipment installed. Datasheets referred to can be downloaded here.

The following information is updated monthly and can be downloaded in spreadsheet form here:

  1. Cumulative AC energy delivered to the grid (at 330kV Gullen Range Wind Farm connection point)
  2. Summary of solar resource and weather data

The regional reference electricity price is published by AEMO and can be viewed here on their website.

Regular updates on the price of Large-Scale Generation Certificates can be accessed on the Clean Energy Regulator website here.

Contact us if you have any queries about this information.